Street and utility improvements are coming to Medicine Lake in 2024!
Scroll down to learn more.
About the Project
The City of Medicine Lake is being proactive in addressing its aging infrastructure that cause maintenance issues and reliability concerns. The city is making long-term public infrastructure improvements. Construction started in spring 2024.
The following are included as part of the Street and Utility Project improvements:
Complete street rehabilitation on Peninsula Rd, Kaiser Ave, and Colonial Cir
Watermain installation (connected to City of Plymouth system)
New fire hydrants
Sanitary sewer improvements
Replacement of trail along S. Shore Drive
Parking lot upgrades to Jevne Park
Irrigation upgrades at Memorial Park
And other improvements!
Explore this website to learn more about all the improvements.
NEW! Construction Updates
Updates are posted on the Construction page. Updates include detailed information on anticipated construction activities for the week.
All construction activities are paused until Spring 2025.
The contractor completed all the required construction obligations by the 2024 contract completion date of November 30, 2024, with the exception of paving the trail through Memorial Park. In light of this, the contractor agreed to plow the gravel trail all winter.
In the spring, the contractor will return to complete construction. The final completion date per contract is June 30. 2025
The remaining work consists of the following items:
Topsoil and seeding all disturbed areas
All “punch list” repair items. There is a fairly extensive list of repairs that need to be fixed in the spring, many of which are located on private property. Once those are completed, we hope to confirm the repairs are satisfactory to each property owner
Landscaping and irrigation in Memorial Park
Pave the Memorial Park trail
Raised crosswalks
Final signage
Final lift of asphalt (This is typically the last thing done once all the other work is completed. Includes speed bumps. In Minnesota, asphalt plants typically do not open until mid-May, but this is entirely weather dependent.
Final pavement striping after the pavement is completed.
Timeline
December 2023 - Contractor bids received
January 2024 - City Council hires contractor
March 2024 - Public Meeting on March 18
April 2024 - Construction starts
Early Fall 2024 - Water service available for connection
November 2024 – Substantially completed
June 2025 - Final completion
Please note: This timeline and project event dates may change as needed.
For more information about construction visit the ‘Construction’ page.
Benefits
The Street and Utility Project will provide the following benefits:
Ensures the long-term vitality of the Medicine Lake community
Rehabilitates aging infrastructure
Improves road safety for all users
Improves mobility for pedestrians and bicyclists
Upgrades to the sanitary sewer infrastructure
Improves fire protection with new fire hydrants
Provides municipal drinking water
Project Groundbreaking - April 1, 2024
The City held an official groundbreaking for the project on April 1. The event was hosted at Jevne Park.
"This project represents a monumental achievement for Medicine Lake, a city with a population of just 371, undertaking a $7 million dollar project. It's a testament to what communities can achieve with the right support and partnerships,"
- Medicine Lake Mayor Chris Heim